November 7, 2011
The basement floor was cemented.

November 5,6
The outside walls are being finished and the first windows went in.

October 29,30
October 22,23
October 15,16
October 8,9,10
Thanksgiving long weekend - the group of volunteers are starting!
September 2011
The hall was moved onto the foundation.
September 2, 2011
The foundation going up.
August 31, 2011
The foundation was started.
August 28, 2011
The foundation footing was poured.
August 20,2011
The hole for the foundation was started.
July 2011
The building was reinforced. The ceiling inside was removed and restored to the original height. The building was then lifted and set aside to permit the digging of the foundation.
June 17, 2011
The side kitchen is removed.

June 12. 2011
A week into the project. This stage of the job is very laborious but progressing well. The crawl space under the building is very low making digging by hand slow and wet.
June 6, 2011
The contractor is starting.

June 2, 2011
Progress! The kitchen was packed up today. A few pictures to remind us of the way the Hall looked.


May 31, 2011
The contract is signed!
Phase 1 - moving the Heritage section of the building, digging and foundation, placing the building back onto the new foundation & renovation of this section.
Phase 2 - We will be asking for volunteers to help build the additions to the main structure.
May 30, 2011
Negotiations are underway. The start date is quickly approaching.

November 3, 2010
We have the PERMIT!!!

Discussions are underway with the builder to have everything in place for a Spring start as soon as conditions allow.
The plans are READY, the Architect is SET and all the paperwork is on the GO! The permits are being prepared and any necessary papers tha are still outstanding are being worked on. It looks like we will start as soon as the weather permits.
The Terra Cotta Community Centre as it looked until May 2010
The "Heritage " portion will be preserved and eventually returned to its original appearance.